Expenses Not Covered by Grants



StatusTask1st Priority
2008AirsideDoneBuilt Pilot's Lounge$10,000
2008AirsideDoneGenerator for Fuel Farm$6,000
2008AirsideDoneMove Customs Trailer$5,000
2008AirsideDonePaint GA Hangars$1,000
2008AirsideDoneShade over Vehicles$2,500
2008EquipmentDonePurchase Bobcat$22,000
2008EquipmentDoneUpgrade Aircraft Handicap Ramp$6,500
2008LandsideDoneSchematic Design Maintenance Hangar$50,000
2008SecurityDoneReplace 5 Computers$12,000
2008SecurityDoneReplace/Upgrade Existing Gate$10,000
2008SecurityDoneUpgrade Badging Camera System$7,000
2008SecurityDoneUpgrade Ops Furniture$3,000
2008TerminalDoneBeacon Display Case$7,400
2008TerminalDoneBig Digital Clocks$1,500
2008TerminalDoneConcrete Furniture$1,300
2008TerminalDoneFloor Scrubber$4,900
2008TerminalDoneMilitary Lounge Furniture$3,000
2008TerminalDonePaint terminal walls inside$15,000
2008TerminalDonePurchase Defribralators$2,000
2008TerminalDoneRe-Wire IT Cabling$7,000
2008TerminalDoneRemodel Event Center$6,650
2008TerminalDoneReplace AC Units - Phase 1$10,000
2008TerminalDoneUpgrade Admin Furniture$25,000
2008TerminalDoneUpgrade Printers$4,000
2008TerminalDoneUPS systems Install/Replace$5,000
2009AirsideDoneInstall Tie Downs in T-Shades$10,000
2009AirsideDoneMove FAA Trailer$5,000
2009AirsideDoneRehab Rolle Field$80,000
2009EquipmentDonePurchase verticle lift for inside terminal$13,000
2009LandsideDoneRe-furbish SWF vacated buildings$45,000